The City of Chicago will accelerate the construction of a new concourse at O’Hare International Airport (ORD), breaking ground on the first phase of Concourse E in late 2026 to ensure sufficient gate capacity ahead of a massive terminal replacement project. The revised construction sequence prioritizes new gates to maintain operational stability during the demolition of the existing Terminal 2.

In a press release issued on August 20, 2026, the Chicago Department of Aviation (CDA) and Mayor Brandon Johnson outlined the updated timeline for the $8.8 billion ORDNext modernization program. By fast-tracking Concourse E, the airport aims to support increased flight volumes for hub carriers United Airlines (UA) and American Airlines (AA) before the centerpiece O’Hare Global Terminal (OGT) begins construction in 2029.

Revised timeline and gate capacity

The ORDNext program is designed to increase overall gate capacity at the airport by 14 percent. The newly announced sequence focuses heavily on bringing satellite concourses online before disrupting central terminal operations.

Construction on The New Concourse D began in August 2025. The CDA finalized a Guaranteed Maximum Price for the facility in June 2026, coming in $21 million below the approved budget. Concourse D is scheduled for completion in late 2028 and will provide 19 new gates.

The New Concourse E will be built in two phases. The first phase will break ground in late 2026 and open in 2030, adding 14 gates. The second phase will add 10 more gates and is scheduled for completion in 2034. Once fully built, Concourse E will span approximately 460,000 square feet and house 24 gates.

“Chicago is not waiting to build the O’Hare our residents, businesses and visitors will need for the next generation. By moving forward with New Concourse E this year, we are adding gates where they are needed, keeping this historic modernization moving, and creating a clear path to deliver the O’Hare Global Terminal, the centerpiece of ORDNext, as quickly as possible.” — Brandon Johnson, Mayor of Chicago

Paving the way for the Global Terminal

The decision to advance Concourse E alters a previous 2024 compromise plan. According to reporting by the Daily Herald, the prior sequence would have seen Concourse D built first, followed by a phased construction of the global terminal, and finally Concourse E. The updated strategy ensures that Concourse E provides necessary relief capacity before Terminal 2 is demolished.

Construction on the O’Hare Global Terminal is now scheduled to begin in 2029 and conclude in 2033. DePaul University aviation expert Joseph Schwieterman told the Daily Herald that the revised plan averts what would have been a highly disruptive situation during the construction of the new global terminal.

The resequencing also offers logistical advantages. CDA Communications Director Kevin Bargnes noted to the Daily Herald that the new timeline allows crews to build the tunnel connecting Concourses D and E more efficiently, resulting in overall cost savings for the project.

CDA Commissioner Mike McMurray stated in the press release that starting Concourse E now allows the airport to stay ahead of growth rather than reacting to it. He noted the initial 14 gates will provide the flexibility required to maintain safe and efficient airline operations during the most complex phases of the ORDNext program.

Airline support and operational impact

The capacity additions come as O’Hare experiences high summer demand. The CDA reported the airport is handling nearly 100 more daily departures this summer compared to July 2025, driven by operational expansions from both United and American.

Both hub carriers expressed support for the revised construction sequence. Omar Idris, Vice President of ORD for United Airlines, stated the airline supports a plan that brings new capacity online sooner and maintains efficient operations throughout the construction period.

Amanda Zhang, Vice President of Corporate Real Estate for American Airlines, called the O’Hare Global Terminal a landmark project that will redefine the customer experience. She noted that advancing the terminal efficiently and responsibly remains a shared priority for the airline and the city.

AirPro News analysis

We view the revised ORDNext sequencing as a pragmatic pivot by the Chicago Department of Aviation. Attempting to construct the O’Hare Global Terminal without first securing the relief valve of Concourse E would have likely constrained hub operations for United and American, leading to congestion and potential schedule reductions. By prioritizing gate capacity through the satellite concourses, the city mitigates the operational risk inherent in demolishing a central facility like Terminal 2 at one of the world’s busiest airports. The $21 million budget underrun on Concourse D also suggests the CDA is currently managing the massive capital program with effective financial oversight, a critical factor as the project moves toward the more complex global terminal phase.

Sources: Chicago Department of Aviation

Photo Credit: Chicago Department of Aviation

See more AirPro News in Google. Add AirPro News as a preferred source and our stories will appear more often in your Top Stories.
Continue Reading
Click to comment

Leave a Reply

Route Development

Bristol Airport Renews Level 4+ Carbon Accreditation

Bristol Airport renewed its Level 4+ Airport Carbon Accreditation, targeting net-zero operations by 2030 and a 73% emissions cut by 2027.

Published

on

Bristol Airport Renews Level 4+ Carbon Accreditation

Bristol Airport (BRS) has renewed its Level 4+ Airport Carbon Accreditation, maintaining its certification under the global carbon management programme as the facility targets net-zero operations by 2030.

The renewal, announced in an October 1, 2026 press release, confirms the airport’s adherence to absolute emissions reduction targets and its ongoing engagement with third parties to address indirect emissions. The Level 4+ status, administered by Airports Council International (ACI), requires airports to align their carbon management strategies with the Paris Agreement and offset residual direct emissions using internationally recognized carbon credits.

Sustaining the net-zero pathway

The Level 4+ designation, known as “Transition” within the ACI framework, requires airports to establish absolute reduction targets for Scope 1 and Scope 2 emissions. Bristol Airport has set an interim target to cut its direct emissions by 73 percent by 2027, relative to a 2019 baseline, on its way to achieving net-zero airport operations by 2030.

Clare Hennessey, Director of Planning and Sustainability at Bristol Airport, stated that the renewal validates the facility’s operational changes while highlighting the need for broader industry cooperation.

“We are proud to maintain our position at the forefront of airport sustainability and to renew our Level 4+ Airport Carbon Accreditation. Reaching Level 4+ demonstrates the progress we are making to reduce emissions from our own operations, while recognising that meaningful decarbonisation requires collaboration across the aviation industry and our wider region,” Hennessey said.

Hennessey added that the airport’s focus remains on reducing emissions, investing in new technologies, and working with partners to support the transition toward a more sustainable aviation industry.

Infrastructure and Scope 3 investments

To meet its direct emissions targets, Bristol Airport has invested heavily in terminal infrastructure. On March 16, 2026, the airport announced a £10 million investment into a new energy centre designed to remove gas boilers from the terminal and provide more resilient, efficient energy infrastructure. The airport took delivery of the completed facility over the summer of 2026.

Addressing Scope 3 emissions, which encompass indirect emissions from flights and surface transport, remains a primary challenge for airport operators. Bristol Airport actively targets these emissions through its Aviation Carbon Transition (ACT) Programme. The initiative funds research and development into zero-emission flight and local environmental enhancements.

On September 24, 2026, the airport announced the three successful projects for its 2026 ACT Programme funding. The 2026 funding pool totaled £150,000, with most individual awards capped at £32,000. The selected projects include “Falcon: Airport Wind,” which focuses on low-height wind power generation, and “Supercool: Hydrogen Turnaround and Cold Chain,” a digital twin simulation for hydrogen-electric aircraft operations. A third project focuses on the direct air capture of carbon locally.

The Airport Carbon Accreditation framework

The Airport Carbon Accreditation scheme is the only institutionally endorsed, global carbon management certification programme for airports. Bristol Airport first achieved Level 4+ status on December 14, 2023, becoming the first regional airport in the United Kingdom to reach that tier. The milestone coincided with the publication of the airport’s 2023 to 2028 Sustainability Strategy, which outlines its approach to reducing emissions, supporting zero-emission flight development, and contributing to the regional economy.

The accreditation framework continues to evolve alongside global climate targets. In late 2023, during the COP28 climate summit, ACI introduced a new Level 5 accreditation to recognize airports that achieve and maintain a net-zero carbon balance for Scope 1 and 2 emissions while actively driving Scope 3 reductions. Bristol Airport’s current strategy focuses on maintaining its Level 4+ status as it builds the infrastructure required to reach its 2030 net-zero target and its 2027 interim goal of cutting direct emissions.

Photo Credit: Bristol Airport

See more AirPro News in Google. Add AirPro News as a preferred source and our stories will appear more often in your Top Stories.
Continue Reading

Route Development

SATS and Tocumen Airport Sign MOU for Cargo City Project

SATS and Panama’s Tocumen Airport signed an MOU to develop the 124-hectare Tocumen Cargo City, targeting $300M in investment.

Published

on

SATS and Tocumen Airport Sign MOU for Cargo City Project

Singapore-based ground handler SATS Ltd. and Panama’s Aeropuerto Internacional de Tocumen, S.A. (PTY) signed a Memorandum of Understanding (MOU) on October 5, 2026, to jointly develop air cargo facilities and handling operations.

The agreement, announced in a press release by SATS, aims to strengthen trade connectivity between Asia and the Americas by leveraging SATS’ global logistics network and Tocumen’s position as a central Latin American aviation hub. The collaboration will specifically target the development of the planned Tocumen Cargo City project.

Bilateral framework for logistics growth

The MOU was formalized in Singapore during a state visit by Panamanian President José Raúl Mulino, who met with Singapore Prime Minister Lawrence Wong between October 3 and October 5, 2026. The discussions centered on deepening bilateral cooperation across logistics, trade, and maritime hubs.

Jose Ruiz Blanco, General Manager of Tocumen International Airport, highlighted the structural similarities between the two nations’ economic models.

“Panama and Singapore share a natural role as strategic gateways for global trade and connectivity,” Ruiz Blanco said in a statement released by the Panamanian government. “Having seen Singapore’s logistics development firsthand, I understand the value that a long-term vision has brought to its growth. This understanding with SATS gives us an opportunity to explore new capabilities for Tocumen, strengthen our cargo platform and expand commercial connectivity between Asia-Pacific and the Americas.”

SATS President and Chief Executive Officer Kerry Mok emphasized the role of ecosystem partnerships in building trade hubs.

“Drawing on our experience across major cargo gateways and our global network of over 225 stations in 27 countries, SATS is pleased to partner PTY as it advances its vision for Panama,” Mok said. “Together, we will explore opportunities to strengthen cargo capabilities, improve the movement of goods and support growing trade between Asia and the Americas.”

The Tocumen Cargo City development

The operational focus of the MOU centers on Tocumen Cargo City, a major infrastructure initiative officially presented by Panamanian authorities on January 17, 2024. The 124-hectare development forms a core component of the airport’s 2015-2035 Master Plan.

The project is designed to establish a new cargo terminal and an adjacent logistics zone operating under a free trade zone regime. According to project outlines, the initial phases of the Cargo City development are expected to attract $300 million in investments.

Tocumen International Airport, widely marketed as the “Hub of the Americas” and the primary base for Copa Airlines (CM), has experienced sustained growth in its freight operations. In 2025, the airport handled 248,455 metric tons of cargo. This represented a 15 percent year-over-year increase, positioning Tocumen alongside Lima’s Jorge Chávez International Airport as one of the fastest-growing air freight hubs in Latin America.

SATS’ global consolidation strategy

For SATS, the agreement in Panama represents a continuation of an aggressive international expansion strategy. Historically focused on the Asia-Pacific region, the company fundamentally altered its market position on April 3, 2023, when it completed the acquisition of Worldwide Flight Services (WFS) from Cerberus Capital Management.

The €2.25 billion transaction transformed SATS into the world’s largest air cargo aircraft handler by volume and geographic footprint. The combined entity now operates across 225 stations in 27 countries, providing food solutions and gateway services to a broad portfolio of international carriers.

Establishing a formal development framework at Tocumen provides SATS with a strategic entry point to influence infrastructure design and operational standards at a critical juncture between North American and South American markets.

AirPro News analysis

While MOUs often serve as non-binding frameworks to explore future contracts, this agreement aligns two highly complementary logistics strategies. SATS is actively working to integrate its massive WFS acquisition into a cohesive global network, and securing a foothold at the primary aviation hub of the Americas provides a critical link for trans-Pacific e-commerce and specialized freight. For Tocumen, partnering with the world’s largest cargo handler lends immediate operational credibility to its $300 million Cargo City project. Involving an operator of SATS’ scale early in the development cycle could optimize facility design for high-throughput handling and potentially accelerate tenant acquisition and foreign direct investment.

Photo Credit: SATS Ltd.

See more AirPro News in Google. Add AirPro News as a preferred source and our stories will appear more often in your Top Stories.
Continue Reading

Route Development

Almaty Airport Secures $670M Syndicated Loan for Next Phase

Bank of America arranges $670M financing for Almaty Airport, with EDB and TIF committing $120M for terminal and cargo upgrades.

Published

on

Almaty Airport Secures $670M Syndicated Loan for Next Phase

The Eurasian Development Bank (EDB) and the Turkic Investment Fund (TIF) have committed a combined $120 million to a $670 million syndicated financing package arranged by Bank of America to fund the next phase of modernization at Kazakhstan’s Almaty International Airport (ALA).

Announced in separate press releases on September 28 and 29, 2026, the financing shifts the airport’s development focus toward upgrading its domestic terminal, expanding cargo aircraft capacity, and improving airside infrastructure following the 2024 opening of a new international facility.

Syndicated financing structure

The $670 million club financing package, which matures in 2033, brings together multilateral development banks and commercial lenders to support infrastructure investments in Kazakhstan. The EDB is acting as a senior co-lender with a $100 million contribution, while the TIF is committing up to $20 million to the syndicate.

Other participating financial institutions include Merrill Lynch International, Société Générale, and several local Kazakhstan banks.

“We have consistently supported the development of Almaty Airport and are pleased to continue this work as part of the new Bank of America syndicate,” said Nikolai Podguzov, Chairman of the Management Board of the Eurasian Development Bank. “The broader group of participating lenders underscores confidence in Kazakhstan’s infrastructure assets and creates additional opportunities to attract international capital to major projects in the country.”

Shifting focus to domestic and cargo operations

The new capital injection will fund the next phase of the airport’s capital investment program. With the new international terminal now operational, airport operator TAV Airports is redirecting resources to modernize the existing domestic terminal.

The financing will also cover significant airside infrastructure improvements. Planned upgrades include the construction of new aircraft de-icing facilities and a major expansion of the airport’s cargo terminal to support growing freight volumes.

Almaty Airport’s capacity and regional role

Almaty International Airport ranks as the largest aviation hub in Central Asia and handles approximately two-thirds of Kazakhstan’s air cargo. The facility serves as the home base for national carrier Air Astana and occupies a strategic position on the Trans-Caspian International Transport Route, also known as the Middle Corridor, linking China and Europe.

In 2021, a consortium of international financial institutions including the EDB, DEG, the European Bank for Reconstruction and Development (EBRD), and the International Finance Corporation (IFC) financed the airport’s initial expansion. That project culminated in the June 2024 commissioning of a new international terminal, which increased the airport’s annual design capacity from 3 million to 14 million passengers.

The facility is already approaching those new limits. Passenger traffic at Almaty reached 12 million in 2025, with the airport serving more than 32,000 passengers per day. The airport is operated by Türkiye-based TAV Airports, which manages 15 airports across eight countries. TAV’s majority shareholder is France-based Groupe ADP, the operator of the three main airports in Paris.

AirPro News analysis

The rapid approach to the 14 million passenger capacity limit just one year after the new international terminal opened underscores the urgency of this second phase of investment. By securing long-term capital through 2033, TAV Airports and its partners are positioning Almaty to capture growing East-West transit traffic along the Middle Corridor. We view the specific focus on cargo expansion and de-icing facilities as critical steps to eliminate operational bottlenecks that were sidelined during the international terminal construction, ensuring the hub can sustain its rapid growth trajectory.

Photo Credit: Eurasian Development Bank

See more AirPro News in Google. Add AirPro News as a preferred source and our stories will appear more often in your Top Stories.
Continue Reading
Advertisement

Follow Us

AirPro Atlas

Explore aviation on one 3D globe
4,000+ airports, 420+ active airlines, 180+ launch pads and 30 aircraft plants and boneyards, with live weather and launch countdowns.
Open the Atlas

aviation newsletter

Latest

Categories

Tags

Popular News