HondaJet Echelon First Wing Complete, Certification Delayed to 2031

Honda Aircraft completes first Echelon wing structure but delays first flight to 2028 and type certification to 2031 due to supplier issues.

Published

on

Photo: Honda Aircraft Company

Honda Aircraft Company has completed the first wing structure for the HondaJet Echelon test aircraft, while simultaneously announcing a two-year delay to the light jet’s development timeline.

In a press release issued on September 15, 2026, the manufacturers confirmed the manufacturing milestone at its Greensboro, North Carolina, facility. The company also disclosed that supplier-related schedule adjustments have pushed the targeted first flight of the HA-480 to 2028, with type certification and initial deliveries now slated for 2031.

Manufacturing progress and facility expansion

Construction of the first Echelon wing began in February 2025, according to reporting by Aviation International News. Honda Aircraft currently has five wing structures in various stages of final assembly. The company reported that 70 percent of the parts required for the first aircraft assembly are currently on hand at the Greensboro facility.

Mainline final assembly is targeted to begin in early 2027. This work will take place within an 88,400-square-foot manufacturing space provisioned specifically for the Echelon program.

“Completion of the first wing assembly represents an important achievement as we continue advancing testing, systems integration, and equipment qualification activity across the program,” said Amod Kelkar, Senior Vice President, Chief Commercial Officer and HondaJet Echelon Program Leader.

Schedule adjustments and systems integration

The revised timeline represents a shift from the original targets of a 2026 first flight and 2028 certification. Honda Aircraft attributed the delay to schedule adjustments involving tier-one suppliers and ongoing development activities.

Speaking to Aviation International News, Assistant Program Leader Vinicius Souza noted that the company has completed the bulk of the design work and is now primarily focused on the industrialization phase of the program.

System integration is actively underway at the company’s Integrated Test Facility. Engineers are utilizing a fully operational cockpit test environment to validate software and hardware. A second cockpit is currently being commissioned to evaluate key aircraft systems prior to the start of flight testing.

Aircraft specifications and market demand

The HondaJet Echelon is designed to be certified as an amendment to the existing HondaJet HA-420 type certificate. It retains the signature over-the-wing engine mount configuration, utilizing Williams International FJ44-4C engines.

The aircraft targets a maximum cruise speed of 450 knots true airspeed (KTAS) and a maximum cruise altitude of Flight Level 470 (FL470). It is designed to carry up to 11 occupants, configured as either one crew member and 10 passengers, or two crew members and nine passengers. With one crew member and four passengers, the targeted National Business Aviation Association (NBAA) instrument flight rules (IFR) range is 2,625 nautical miles.

The flight deck will feature advanced avionics, including auto-throttle, emergency autoland, autobrake, and a Runway Overrun Awareness and Alerting System (ROAAS). Honda Aircraft reported holding more than 530 signed letters of intent for the Echelon. Kelkar stated that this customer confidence reflects the aircraft’s planned combination of range, comfort, and single-pilot capability.

AirPro News analysis

We note that the two-year schedule adjustment for the HondaJet Echelon aligns with broader aerospace industry trends, where supply-chain constraints and tier-one supplier bottlenecks frequently dictate industrialization timelines. By certifying the HA-480 as an amendment to the HA-420 type certificate, Honda Aircraft mitigates some regulatory risk. However, the integration of new automated systems like autoland and ROAAS into a larger airframe still requires extensive validation. The robust backlog of over 530 letters of intent suggests that the market is willing to absorb the delay for a single-pilot jet with transcontinental range.

Sources: Honda Aircraft Company

See more AirPro News in Google. Add AirPro News as a preferred source and our stories will appear more often in your Top Stories.
Continue Reading
Click to comment

Leave a Reply

Business Aviation

Los Angeles Approves Two Sky Harbour Hangar Campus Leases at VNY

The Los Angeles City Council approved two Sky Harbour ground leases at Van Nuys Airport covering over 25 acres and about 300,000 square feet.

Published

on

Los Angeles Approves Two Sky Harbour Hangar Campus Leases at VNY
Photo: Sky Harbour

The Los Angeles City Council has approved two ground leases for Sky Harbour Group Corporation to build Home Base Operator (HBO) hangar campuses at Van Nuys Airport (VNY). The company says the two sites total more than 25 acres and expects to build about 300,000 rentable square feet of hangar, office, lounge and storage space there.

Sky Harbour announced the approval in a press release dated November 9, 2026, and said it expects the leases to be formally signed in the coming weeks. For scale, in its third quarter results a day later, Sky Harbour said it was operating 1.04 million square feet of hangar and associated office and support space across its network.

What the Van Nuys leases cover

Sky Harbour, based in West Harrison, New York, is building a nationwide network of HBO campuses for business aircraft. Its Home-Basing offering is meant to give private and corporate aircraft owners top physical infrastructure and dedicated service for based aircraft, with the aim of the shortest possible time to wheels-up.

Tal Keinan, Sky Harbour’s CEO, linked the Van Nuys move to demand from local operators:

“Van Nuys operators have actively been seeking the Sky Harbour Home Base Operator model, and we are excited to deliver it.”

Keinan thanked the Los Angeles City Council, the Board of Airport Commissioners and the Van Nuys and Los Angeles World Airports teams, and said “Sky Harbour plans to bring new and lasting value to the airport,” as well as to Los Angeles business aviation and the San Fernando Valley community. The company said it expects the developments to bring substantial private investment to VNY and to create or sustain hundreds of local construction and operations jobs. It did not disclose the investment amount or a construction schedule for the two sites.

Van Nuys and the Los Angeles market

Sky Harbour’s release calls VNY the main business aviation gateway to Los Angeles. Los Angeles World Airports (LAWA), which owns VNY and Los Angeles International Airport (LAX), describes Van Nuys as one of the world’s busiest general aviation airports, averaging over 217,000 takeoffs and landings a year. The 730-acre airport has two parallel runways of 8,000 feet and 4,000 feet, an FAA tower and more than 100 businesses on the field.

According to LAWA, four major fixed-base operators (FBOs) are based at Van Nuys: Castle & Cooke Aviation, Clay Lacy Aviation, Jet Aviation and Signature Aviation. They offer aircraft storage and parking, fuel, sales, flight instruction, charter and maintenance, and some sublease land and buildings to other tenants. LAWA’s airport system is overseen by a Board of Airport Commissioners appointed by the Mayor of Los Angeles.

Van Nuys follows a Sky Harbour lease elsewhere in Southern California. In November 2025, the City of Long Beach said its City Council had voted 8 to 0 to approve a 50-year lease with Sky Harbour for a $60 million private jet campus on approximately 17 acres at Long Beach Airport (LGB), with hangars for corporate jet tenants, a terminal and office complex and an open-air restaurant.

Where Sky Harbour’s network stands

In its third quarter release on November 10, 2026, Sky Harbour reported consolidated revenue up about 45% from the third quarter of 2025. It raised its year-end 2026 revenue guidance to a range of $44 million to $48 million, from $42 million to $46 million, and lowered its adjusted EBITDA guidance to $0 to $4 million from $4 million to $6 million, citing costs tied to opening its Bradley International Airport (BDL) campus in early December and the delay of Dallas Addison Airport (ADS) Phase 2 into the first quarter of 2027.

The company said BDL, in Hartford, Connecticut, is expected to be completed by December 4, 2026. Campuses at Salt Lake City International Airport (SLC), Hudson Valley Regional Airport (POU) and Orlando Executive Airport (ORL) are under construction, and work at Washington Dulles International Airport (IAD), Trenton-Mercer Airport (TTN) and Chicago Executive Airport (PWK) is scheduled to begin in late 2026. In California, Sky Harbour reported Phase 1 at San Jose Mineta International Airport (SJC) at 132% economic occupancy, with the yet-to-be-built Phase 2 100% pre-leased.

Keinan said in the results release that “Sky Harbour’s growing footprint at tier 1 airports represents the early results of a multi-year effort.” The next step at Van Nuys is the formal execution of the two leases, which the company expects within weeks.

See more AirPro News in Google. Add AirPro News as a preferred source and our stories will appear more often in your Top Stories.
Continue Reading

Business Aviation

Airbus Corporate Helicopters Debuts ACH Line Interior on the ACH130

ACH has introduced its ACH Line cabin on the ACH130, a layout first shown on the ACH140 concept, with Air Delta as launch customer.

Published

on

Airbus Corporate Helicopters Debuts ACH Line Interior on the ACH130
Photo: Airbus Corporate Helicopters

Airbus Corporate Helicopters (ACH) has introduced its new ACH Line cabin design on the ACH130 fleet, the official operational debut of a layout first shown as a cabin concept for the ACH140 at Verticon. ACH unveiled the interior at an event in Sappada, in the Italian Alps, where the launch customer’s representative viewed it during demonstration flights over the Dolomites.

In a press release dated November 12, 2026, from Trento, Italy, ACH said the design combines improved cabin ergonomics, operational flexibility and better travel features for corporate and private operators worldwide. The company says the layout sets a new standard for style and function across the ACH range.

Who built the ACH130 Line cabin

Airbus Helicopters in Italy led the engineering and certification work for the new interior. It partnered with two interior specialists, F/LIST and Maison Borghino, on the precision and cabin outfitting of the aircraft.

Nicolas Boltoukhine, Head of ACH, said the new ACH Line look and feel will, “for the first time, offer a visual consistency across our entire range.” He explained that this gives all ACH Line aircraft the ACH brand’s look and a standard level of quality and comfort across all ACH types.

The launch customer was represented at the Sappada event by Maicol La Regina, CEO of Air Delta. ACH did not disclose how many ACH130 aircraft Air Delta has ordered or when deliveries with the new interior begin.

From the ACH140 concept to the ACH130 fleet

The ACH Line design language first appeared on the ACH140, which F/LIST describes as the newest aircraft in the ACH line, unveiled at Verticon 2026 for private and business aviation customers. AirPro News covered the ACH140 launch at Verticon 2026 at the time.

F/LIST, a family business headquartered in Thomasberg, Austria, with around 1,250 employees worldwide, builds interiors for business and private jets, yachts and luxury residences. In a press release dated March 9, 2026, it said it designed and manufactured a custom-made cabinet for the ACH140 cabin, with a silk-matt black lacquer body, matt carbon drawer fronts, two cup holders, two storage compartments with leather-covered flaps and holders for an iPhone and an iPad.

According to F/LIST, the ACH Line interior concept was developed in close collaboration with Airbus and supports the new design language with elongated lines and ergonomic elements. F/LIST said customers can choose from a range of materials for color, material and finish, and that series production parts are expected to use a monocoque construction method with autoclave technology.

The ACH130 release does not say whether the ACH130 cabin uses the same cabinet or materials as the ACH140 cabin concept shown at Verticon.

See more AirPro News in Google. Add AirPro News as a preferred source and our stories will appear more often in your Top Stories.
Continue Reading

Business Aviation

THC Firms Up Bombardier Order for 12 Jets With 48 Options

The Helicopter Company signed firm agreements for 12 Bombardier jets worth about US$568 million at list prices, with options for 48 more.

Published

on

THC Firms Up Bombardier Order for 12 Jets With 48 Options
Photo: Bombardier

The Helicopter Company (THC) has converted its July 2026 letter of intent with Bombardier into binding fleet purchase agreements for up to 60 business jets, including a firm order for 12 aircraft valued at about US$568 million at 2026 list prices. Bombardier and THC announced the agreements in Montreal on November 13, 2026.

The firm order covers five Challenger 3500, five Global 5500 and two Global 8000 aircraft, with options for 48 more. In its press release, Bombardier said the exercise of those options “would be at the discretion of the client.” The companies describe the agreement as the largest transaction of its kind in Saudi Arabia, and it marks THC’s entry into business aviation.

From a Farnborough letter of intent to a firm order

THC and Bombardier first signed a Letter of Intent (LOI) at the Farnborough International Airshow in the United Kingdom, which AirPro News reported as THC’s Bombardier letter of intent. According to the Public Investment Fund (PIF), which owns THC, the LOI pointed to a firm order for 12 aircraft, five Challenger 3500s, five Global 5500s and two Global 8000s, with purchase options for 48 more jets of the same models.

The November agreements keep that mix unchanged. The new release puts a value on the firm portion, about US$568 million at 2026 list prices, and states that the 48 options are at THC’s discretion. The release does not give a delivery schedule for the 12 firm aircraft.

PIF said the July signing was attended by Captain Arnaud Martinez, CEO of THC, Muhammad Ovais Yousuf, Head of Aviation & Security for PIF’s MENA Investments Division, and Bombardier leaders including CEO Éric Martel and Chairman Pierre Beaudoin.

THC’s move from helicopters to business jets

THC was established as part of PIF’s strategy to open new sectors in Saudi Arabia in support of Vision 2030, according to the company profile in the release. PIF describes THC as a PIF company founded in 2018. THC has operated since mid-2019, describes itself as the Kingdom’s leading commercial helicopter operator, and has more than 60 aircraft serving emergency medical services (EMS), aerial work, private charters and tourism.

When THC announced its business aviation launch at Farnborough, PIF said the company would move into chartering and managing business jets. PIF said the business jet segment targets Saudi and regional demand, with the aim of becoming the region’s leading business aviation operator and the preferred national carrier for private charters. The new release says the Bombardier order extends THC’s services to meet growing demand for premium business travel within Saudi Arabia and across the region.

THC sits within PIF’s Tourism, Travel & Entertainment ecosystem. PIF also launched the national airline Riyadh Air and owns the aircraft leasing company Avilease.

“This transaction marks THC’s entry into business aviation,” Martinez said in the release. He described it as the next step in building an integrated aviation operator for the Kingdom, and said demand for business aviation services in Saudi Arabia and the wider region continues to grow. He added that THC looks forward to bringing the aircraft into service as it continues to support the development of the Kingdom’s aviation sector under Vision 2030.

Martel called THC’s decision to move forward with the fleet purchase agreements “a meaningful vote of confidence in what our teams deliver every day.” He said Bombardier looks forward to supporting THC as it prepares to launch its business aircraft fleet.

The three Bombardier types in the order

In its account of the LOI, PIF said the planned fleet would span super-midsize, long-range and ultra-long-range jets. The Challenger 3500 carries up to nine passengers and has a range of 3,400 nautical miles (6,297 km). Bombardier says the type suits missions within the Gulf Cooperation Council region and has the lowest direct operating costs in its class.

The Global 5500 seats up to 16 passengers across three living zones and has a range of 5,900 nautical miles (10,927 km), which Bombardier describes as the longest in its category. The Global 8000, Bombardier’s flagship ultra-long-range jet, has a range of 8,000 nautical miles (14,816 km) and four cabin zones. Bombardier says it can fly nonstop between city pairs such as Riyadh and Los Angeles, and that its leading-edge slats allow it to land at up to 30% more airports than its closest rival.

Bombardier’s investment commitment in Saudi Arabia

As part of the partnership, Bombardier said it has committed to a long-term strategic investment that includes a local footprint in Saudi Arabia. The release does not say what form that footprint will take or when it will be in place. At the July signing, Martel said Bombardier planned local investments dedicated to supporting THC’s operations, according to PIF.

Bombardier says its customers operate a fleet of approximately 5,300 aircraft, supported by 10 service facilities across six countries. Its jets are manufactured in aerostructure, assembly and completion facilities in Canada, the United States and Mexico.

See more AirPro News in Google. Add AirPro News as a preferred source and our stories will appear more often in your Top Stories.
Continue Reading
Advertisement

Follow Us

AirPro Atlas

Explore aviation on one 3D globe
4,000+ airports, 700+ active airlines, 180+ launch pads and 30 aircraft plants and boneyards, with live weather and launch countdowns.
Open the Atlas

aviation newsletter

Latest

Categories

Tags

Popular News