San Antonio Airport to Close Terminal B Lanes for Terminal C Construction
San Antonio International Airport will close two lanes at Terminal B in March 2026 to build zero-curb access and a canopy for the new Terminal C.
This article is based on an official press release from the City of San Antonio Aviation Department.
San Antonio International Airport (SAT) is preparing for a significant infrastructure upgrade that will temporarily alter traffic flow for passengers. According to an official press release from the City of San Antonio Aviation Department, the airport will commence construction on its terminal curbside lanes as part of the broader Terminal Development Project.
We note that this initiative, falling under the ELEVATE/SAT program, aims to expand the airport’s capacity to accommodate future regional growth. The upcoming work represents a critical step in modernizing the facility and preparing for the addition of a new terminal.
Beginning on March 23, 2026, the airport will initiate the first phase of a multi-phase lane closure plan. The city’s press release indicates that two of the four lanes located at the far end of Terminal B’s upper and lower levels will be closed. This closure is necessary to facilitate roadway modifications that will eventually support the planned Terminal C.
A major focus of Phase I is the construction of a zero-curb transition connecting the existing roadway to the future Terminal C. Airport officials highlighted in the release that this design prioritizes accessibility, creating a seamless, barrier-free path from the street directly into the terminal. Additionally, crews will begin erecting the Terminal C canopy, which is designed to offer weather protection and enhance the overall curbside experience once finalized.
“This next phase of SAT’s transformation represents far more than infrastructure. For millions of travelers each year, SAT is the first and last impression of our city and today is a next step in building an experience that reflects the energy and hospitality of San Antonio. All passengers deserve an airport experience that is accessible and free from barriers.”
With the lane closures imminent, travelers and drivers should anticipate temporary shifts in how they navigate the terminal roadways. To mitigate congestion and ensure a smooth experience, the airport is advising passengers to arrive early.
The aviation department’s release outlines several alternatives to traditional curbside pick-up and drop-off. The Short-Term Parking Garage provides dedicated three-hour spaces, costing $5 for the initial hour and $4 for each subsequent hour. For those waiting to collect arriving passengers, the Cell Phone Waiting Lot remains a free, 24/7 option equipped with complimentary Wi-Fi. Furthermore, the airport stated that key construction activities will be scheduled overnight whenever feasible to minimize disruptions.
The Terminal Development Project at SAT reflects a broader trend among mid-sized U.S. airports racing to modernize aging infrastructure while accommodating surging passenger demand. The ELEVATE/SAT initiative is particularly notable for its emphasis on accessibility,such as the zero-curb transition,which aligns with modern inclusive design standards. By prioritizing barrier-free access and weather-protected canopies, San Antonio is positioning its facilities to compete more effectively for both domestic and international routes, ultimately driving regional economic development. Phase I of the terminal curbside lane closures is scheduled to begin on March 23, 2026, according to the airport’s press release.
Two of the four lanes at the far end of both the upper and lower levels of Terminal B will be closed during the initial phase.
The airport recommends using the Short-Term Parking Garage, which costs $5 for the first hour and $4 for each additional hour, or the free, 24/7 Cell Phone Waiting Lot.
Phase I Details and Timeline
Zero-Curb Transition and Canopy
Passenger Impact and Alternatives
Navigating the Airport During Construction
AirPro News analysis
Frequently Asked Questions
When do the lane closures at San Antonio International Airport begin?
Which lanes are affected by the construction?
What are the alternatives for picking up and dropping off passengers?
Photo Credit: City of San Antonio Aviation Department
Route Development
American Airlines Unveils Terminal C Upgrades at Dallas Fort Worth Airport
American Airlines announces nine new gates and passenger amenities in Terminal C as part of a multiyear modernization at Dallas Fort Worth International Airport.
This article is based on an official press release from American Airlines.
American Airlines is pulling back the curtain on its multiyear modernization efforts at Dallas Fort Worth International Airport (DFW), highlighting significant upgrades coming to the facility. In a recent company press release, the airline detailed the upcoming Terminal C pier, which promises to deliver a smoother travel experience for millions of passengers.
As the carrier celebrates its centennial year in 2026, it is investing billions of dollars into its hometown airport and largest hub. We are seeing a concerted effort by the airline to improve operational resilience and passenger comfort at a critical juncture for the aviation industry.
The newly announced enhancements are part of a broader communication campaign designed to keep travelers informed as various construction milestones are reached at DFW.
According to the official press release, the new Terminal C pier will introduce nine new gates to the DFW hub. This expansion is not just about increasing capacity; it is heavily focused on the passenger experience. The airline notes that the pier will feature new concessions and updated seating arrangements designed for modern travelers.
Additionally, American Airlines highlighted the implementation of a “game-changing bag storage system.” While specific technical details of the baggage system were not fully disclosed in the release, the upgrade aims to streamline luggage handling and reduce connection friction for passengers transiting through the busy Texas hub.
In the release’s accompanying multimedia notes, the airline emphasized the core motivation behind the project:
“The investments in Terminal C are important to enhancing the experience for our customers and team members.”
This sentiment was echoed by Rich Ashlin, American’s Vice President of DFW Hub Operations, who provided a sneak peek of the facilities in the airline’s latest promotional materials. To showcase these developments, American Airlines has launched a shortform video and podcast series titled “Forever Forward at DFW.” The series is intended to take viewers behind the scenes of the extensive construction and modernization projects currently underway.
The press release states that DFW hosts more passengers than any other airport in the American Airlines network. Because of this immense volume, the billions of dollars being invested are crucial for providing schedule certainty and improving the hub’s resilience against severe weather and other operational disruptions.
By bringing customers along for the journey, the airline hopes to build anticipation and demonstrate its long-standing commitment to the Texas region and its broader global network.
As American Airlines marks its 100th anniversary in 2026, securing the operational efficiency of its primary DFW hub is a strategic imperative. The airline currently operates more than 6,000 daily flights globally, serving over 200 million customers annually. A significant portion of that traffic flows directly through Dallas Fort Worth.
We view the Terminal C pier expansion, and the accompanying transparency campaign, as a proactive measure to manage passenger expectations during a period of heavy construction. By framing the disruptions as necessary steps toward a modernized future, American Airlines is working to maintain brand loyalty while future-proofing its most vital infrastructure against increasingly unpredictable weather patterns.
How many new gates are being added to Terminal C at DFW? What other amenities are included in the Terminal C upgrade? What is “Forever Forward at DFW”?
Upgrades at Terminal C
New Gates and Passenger Amenities
The “Forever Forward” Initiative
Modernizing the Flagship Hub
AirPro News analysis
Frequently Asked Questions
According to the American Airlines press release, the new Terminal C pier will bring nine new gates to the airport.
The expansion includes new concessions, updated seating, and a new bag storage system.
It is a shortform video and podcast series created by American Airlines to document the multiyear, multibillion-dollar modernization of its Dallas Fort Worth hub.Sources
Photo Credit: American Airlines
Route Development
Messer Sundt Begins $900M Rental Car Project at Nashville Airport
Messer Sundt Joint Venture launches a $900 million rental car facility and parking expansion at Nashville International Airport, part of a $3B upgrade.
This article is based on an official press release from Messer Construction Co.
The Messer Sundt Joint Venture has officially commenced construction on a massive $900 million consolidated rental car (CONRAC) program at Nashville International Airport (BNA). According to an official press release from Messer Construction Co., the project is a major component of the airport’s broader $3 billion “New Horizon” expansion initiative.
Designed to accommodate the rapidly growing passenger traffic in the Nashville region, the progressive design-build project will deliver a significantly expanded rental car complex, a new parking garage, and critical roadway improvements. The joint venture expects to complete the multi-phased development by 2029.
As one of the fastest-growing airports in the United States, BNA is prioritizing capacity and mobility upgrades. We are seeing major infrastructure investments across the aviation sector, and this $900 million commitment underscores the demand for streamlined traveler experiences.
The comprehensive scope of the CONRAC program involves the construction of a six-level facility tailored to modern airport logistics. Based on the project outline provided by Messer Construction Co., the development includes a new parking garage that will provide 3,000 parking spaces, offering travelers direct and easy access to the terminal.
Adjacent to the parking structure, the joint venture will build a 4,700-vehicle consolidated rental car facility. This will be supported by a dedicated Customer Service Building to streamline rental operations. The facility will also feature quick-turnaround areas equipped with fueling stations and car wash capabilities to maintain rental fleets efficiently.
Beyond the buildings themselves, the $900 million investment will fund significant improvements to the airport’s vehicular flow. The project includes new bridges and roadways that will connect Terminal Drive directly to the new CONRAC facility.
Additionally, the construction teams will expand the Terminal Drive “loop road.” The company noted that this expansion is designed to increase capacity for all roadway traffic and improve connections to the surrounding local road network, while also adding infrastructure to support on-airport shuttle operations. The collaboration between Messer Construction Co., Sundt, and the Metropolitan Nashville Airport Authority (MNAA) aims to deliver the project on an aggressive schedule while maintaining environmental performance standards. Project leaders have emphasized the transformative nature of the investment.
“This project is a transformative investment in the future of Nashville International Airport and the region it serves. Our team is proud to partner with Messer Construction Co. and MNAA to deliver a facility focused on the traveler experience while improving operational efficiency and supporting the airport’s continued growth.”
The quote above highlights the dual focus on customer experience and operational capability that the joint venture is bringing to the Nashville market.
Messer Operations Vice President Jeff Banta echoed these sentiments, noting the importance of the final phase of the terminal area roadway improvements.
“We’re excited to partner with Sundt and MNAA to lead the construction of BNA’s new consolidated rental car facility, parking garage expansion and the final phase of the terminal area roadway improvements. Our talented design-build team is proud to be part of improving the traveler experience for the growing Nashville region.”
Banta’s remarks, sourced from the official announcement, reinforce the joint venture’s commitment to supporting the region’s economic and infrastructural growth.
The $3 billion New Horizon program at Nashville International Airport reflects a broader trend among mid-sized and large U.S. hubs racing to modernize aging infrastructure. As passenger volumes continue to break records post-pandemic, airports are increasingly turning to consolidated rental car facilities (CONRACs) to reduce terminal congestion and centralize ground transportation.
By removing rental car shuttles from the main terminal loop and integrating a 4,700-vehicle facility with a 3,000-space parking garage, BNA is positioning itself to handle long-term capacity demands. The $900 million price tag for this specific phase illustrates the high capital costs associated with progressive design-build infrastructure in today’s construction market.
According to the press release, the Messer Sundt Joint Venture’s work on the CONRAC program is estimated to cost $900 million.
The project will be delivered in phases and is scheduled for final completion in 2029. The project includes a new parking garage with 3,000 spaces and an adjoining consolidated rental car facility designed to hold 4,700 vehicles.
Project Scope and Infrastructure Upgrades
Roadway and Mobility Enhancements
Leadership Perspectives on the Expansion
AirPro News analysis
Frequently Asked Questions (FAQ)
What is the total cost of the BNA CONRAC program?
When will the Nashville Airport CONRAC project be completed?
How many vehicles will the new facilities hold?
Sources
Photo Credit: Messer Construction Co.
Route Development
Southwest Airlines Ends Flights at Chicago O’Hare in June 2026
Southwest Airlines will exit Chicago O’Hare and Washington Dulles airports by June 3, 2026, consolidating operations at Chicago Midway.
This article summarizes reporting by CBS News Chicago and Sara Tenenbaum.
Southwest Airlines is officially ending its five-year operational stint at Chicago O’Hare International Airport (ORD). According to reporting by CBS News Chicago, the Dallas-based carrier announced on Friday, March 13, 2026, that it will cease all flights at the major international hub this coming June.
“Southwest Airlines announced Friday that it will stop operating flights out of Chicago O’Hare International Airport in June,” reported Sara Tenenbaum for CBS News Chicago.
The strategic retreat also includes a simultaneous withdrawal from Washington Dulles International Airport (IAD). The final day of service for both airports will be June 3, 2026, marking a significant network optimization effort by the airline. For travelers, this signals a definitive shift back to Southwest’s traditional stronghold at Chicago Midway International Airport (MDW), where the airline plans to consolidate its Chicago-area operations and absorb displaced routes.
The operational cutoff is set for early June. As detailed in official Southwest Airlines travel advisories and highlighted in the CBS News Chicago report, the airline’s final flights out of O’Hare will depart on June 3, 2026. Any itineraries scheduled for June 4 or later will be directly impacted by the closure, while travelers flying on or before June 3 will experience no disruptions.
To mitigate inconveniences, Southwest is offering flexible accommodations for affected passengers. Travelers holding tickets for June 4 and beyond are eligible for full refunds on unused fares. Alternatively, passengers can rebook or fly standby from nearby alternative airports, including Chicago Midway, Milwaukee Mitchell International Airport (MKE), or Indianapolis International Airport (IND).
Southwest’s departure from O’Hare represents a return to its historical strategy. For decades, the airline famously avoided the congestion of O’Hare, choosing instead to dominate the smaller, more manageable Midway Airport. This strategy worked flawlessly for the airline prior to 2021, allowing for rapid turnarounds and high aircraft utilization rates. The carrier only expanded into O’Hare in 2021 during the pandemic to capture shifting market share, making this June exit the end of a five-year experiment.
Now, the airline is doubling down on its South Side hub. Industry research reports indicate that Southwest will increase its capacity at Midway to compensate for the O’Hare exit. The airline plans to operate up to 244 daily departures from Midway, serving more than 80 nonstop destinations. Furthermore, 15 markets previously served from O’Hare will be transferred to Midway, ensuring that Chicago travelers retain access to these routes without losing overall network connectivity.
The decision to exit O’Hare and Dulles does not exist in a vacuum. The broader aviation industry is currently navigating a complex web of operational hurdles, including FAA congestion caps, air traffic controller shortages, and severe aircraft delivery constraints. Airlines are increasingly forced to make tough choices about where to deploy their limited resources, often retreating to core hubs where they maintain dominant market share. Southwest has been forced to make difficult network decisions over the past few years. In April 2024, the airline announced significant capacity reductions at O’Hare and Hartsfield-Jackson Atlanta International Airport, while completely exiting four other markets, including Houston’s George Bush Intercontinental and Syracuse.
During the company’s Q1 2024 earnings call, CEO Bob Jordan attributed those earlier cutbacks to financial underperformance and ongoing delivery delays from Boeing. The 2026 withdrawal from O’Hare appears to be a continuation of this long-term strategy to optimize resources amid constrained fleet growth.
We view Southwest’s exit from O’Hare as a pragmatic admission that the 2021 pandemic-era expansion into ultra-congested legacy hubs has yielded diminishing returns in today’s constrained operating environment. By retreating to Midway, Southwest reclaims its operational reliability and shields itself from the severe air traffic control and congestion issues that frequently impact O’Hare. While the loss of competition at O’Hare may marginally impact fares at that specific airport, Southwest’s aggressive capacity transfer to Midway ensures the broader Chicago market remains highly competitive.
According to Southwest’s travel advisory, the final day of service at Chicago O’Hare and Washington Dulles will be June 3, 2026.
Yes. Passengers with flights booked for June 4, 2026, or later are eligible for full refunds on unused tickets, or they can rebook out of alternative airports like Midway, Milwaukee, or Indianapolis.
No. Southwest is consolidating its operations at Chicago Midway International Airport, where it will increase daily departures and absorb 15 markets previously served out of O’Hare.
Timeline and Customer Accommodations
Managing the June Transition
The Return to Midway
Consolidating Chicago Operations
Broader Industry Challenges
Boeing Delays and Network Optimization
AirPro News analysis
Frequently Asked Questions
When is Southwest’s last day of service at O’Hare?
Can I get a refund if my flight is scheduled after June 3?
Is Southwest leaving Chicago entirely?
Sources
Photo Credit: Southwest Airlines
-
Regulations & Safety2 days agoAir Canada Express Jet Collides with Fire Truck at LaGuardia Airport
-
Commercial Aviation22 hours agoeasyJet to Fit Ultra-Lightweight Mirus Kestrel Seats on 237 New Aircraft
-
MRO & Manufacturing4 days agoAirbus Seeks Damages from Pratt & Whitney Over Engine Delays
-
Defense & Military5 days agoKongsberg Secures NOK 2 Billion Contract Extension for F-35 Components
-
MRO & Manufacturing6 days agoRyanair Opens €25M Maintenance Hangar at Madrid Barajas Airport