Long Beach Airport Begins $37M Concourse Upgrade for 2028 Olympics
Long Beach Airport launches a $37 million concourse enhancement project funded largely by FAA grants, aiming for completion by summer 2027 ahead of the 2028 Olympics.
This article is based on an official press release from the City of Long Beach.
Long Beach Airport (LGB) has officially commenced construction on a comprehensive $37 million Passenger Concourse Enhancement Project. According to an official press release from the City of Long Beach, the groundbreaking ceremony took place on April 24, 2026. The project is strategically timed to modernize the airport’s post-security passenger concourse and upgrade critical infrastructure well ahead of the 2028 Los Angeles Olympic and Paralympic Games.
City officials project that the enhancements will be completed by the summer of 2027. The phased construction plan ensures that the airport will maintain full operations, with no anticipated impacts to commercial flights or gate access during the build period.
We recognize that LGB has built a strong reputation as a relaxed, open-air travel hub in Southern California. This modernization effort aims to preserve that boutique appeal while making necessary updates to a concourse that has accommodated millions of passengers since it originally opened in 2012.
Passenger Experience and Design Upgrades
Enhancing the Southern California Vibe
The modernization effort focuses heavily on improving passenger circulation, comfort, and clarity. Based on the project overview provided by the city, the remodel will encompass the existing 11 gate areas, introducing modernized gate podiums and updated seating configurations featuring integrated electrical charging options.
To further reduce congestion, the airport is updating its queuing layouts, expanding wayfinding signage, and installing new flight information displays. Travelers will also see new flooring and fully updated restrooms throughout the concourse.
Emphasizing the airport’s indoor-outdoor connection, the design includes the creation of new open-air garden areas outside the north and south concourses. The existing central garden will also receive improvements, including additional hardscape, shaded seating, and canopies. Furthermore, the exterior pedestrian canopy will be extended to Pad 11, and a dedicated Service Animal Relief Area will be added to the facility.
“This project represents an important investment in Long Beach’s future and the millions of travelers who choose our award-winning Airport each year. As we prepare to welcome the world for the 2028 Olympic and Paralympic Games, we are ensuring LGB continues to deliver a modern, comfortable and uniquely Southern California travel experience,” stated Long Beach Mayor Rex Richardson in the press release.
Financial Backing and Economic Impact
Federal Funding Secures the Project
A notable aspect of the $37 million enhancement project is its funding structure, which relies heavily on federal grants rather than local tax dollars. According to the city’s financial breakdown, $24.3 million is funded through the Federal Aviation Administration (FAA) Airport Infrastructure Grant program, a component of the Bipartisan Infrastructure Law. The remaining costs will be covered directly by airport revenue.
“As the former Mayor of Long Beach, I know firsthand how important our airport is to the city and our local economy. This federal investment is going to make our world-class airport even better,” noted U.S. Congressman Robert Garcia, who strongly advocated for the federal funding.
Local Job Creation
The economic footprint of the project extends directly into the local community. City estimates indicate that the enhancement project will generate over 190 local construction jobs. This adds to the broader economic impact of the Long Beach Airport Complex, which currently generates an estimated $9 billion in annual economic output and supports approximately 42,000 jobs across the region.
Infrastructure and Sustainability Goals
Building for the Future
Behind the scenes, the project includes comprehensive mechanical, electrical, and plumbing upgrades. Aging air-conditioning components will be replaced, and a new back-up generator will be installed to improve the facility’s operational resilience.
Sustainability is a core focus, with the project establishing a LEED Silver foundation. Upgrades include the conversion to energy-efficient LED lighting throughout the concourse and a strict requirement that 95% of all construction debris be recycled or reused.
The architectural design is being led by PGAL, while PCL Construction Services, Inc. was awarded the $28 million construction contract, which the Long Beach City Council approved on October 14, 2025.
“This refresh is not just aesthetic, it’s about expanding LGB’s reputation as a premier airport that offers travelers an experience that is distinctly Long Beach,” said Fifth District Councilwoman Megan Kerr in the official release.
AirPro News analysis
The impending 2028 Los Angeles Olympic and Paralympic Games are acting as a major catalyst for infrastructure improvements across Southern California’s aviation sector. By completing these upgrades by the summer of 2027, LGB is strategically positioning itself as a highly attractive, low-stress alternative gateway to the much larger and busier Los Angeles International Airport (LAX).
While LGB consistently ranks high for its passenger experience, the current concourse has been heavily trafficked for over a decade. We view these mechanical and spatial upgrades as essential preventative measures. They will allow the airport to handle modern travel demands and larger crowds without sacrificing the boutique appeal that defines its brand.
Frequently Asked Questions
Will the construction impact my flight out of Long Beach Airport?
According to airport officials, construction will be phased to maintain full airport operations. No impacts to commercial flights are expected, and gate access will be fully accommodated throughout the build.
When will the concourse enhancements be completed?
The project is targeted for completion in the summer of 2027, well ahead of the anticipated surge in travel for the 2028 Olympics.
Are local tax dollars funding this project?
No. The $37 million project is heavily subsidized by a $24.3 million FAA grant, with the remaining balance covered directly by airport revenue.